25 November 2008

Ground Beam in Progress - Day 2













My workers continued with fixing the soffit and side formworks for the ground beam and have covered almost half of the building today. After the formworks are in place, the steel reinforcement will be fixed into the formwork before concrete are poured into it. Besides the ground beam, my workers have to construct the ground slab at the same time. The ground slab will be suspended above ground and located in the middle and back middle panels.

18 November 2008

Column Stumps in Progress

After concreting the footings yesterday my workers had started to fix the formworks for the column stumps. The formworks is expected to be in place by tomorrow. My kepala will check the column stumps to make sure they are in alignment with the grids that had been set up as well as at the predetermined level to receive the ground beams . After everything is in order the workers will immediately proceed to concrete the column stumps.