My workers have put in the steel reinforcement into the 2nd. Floor beam formwork and the beams are ready for concreting. I have booked the mobile crane and because tomorrow is a public holiday I have to pay an extra of RM150. I have decided to proceed with the concreting in order to keep progress according to schedule. With progress at 1 week per floor the RC structure will be completed by 1st. week of January 2009. After this I shall proceed with the floor construction consisting of timber joists and cement board. I will not be using RC suspended slab. The 2nd Floor, 3rd Floor and Roof joists will be red meranti timber and act as nesting planks, killing 2 birds with one stone. I will not be showing any floor plans in my blog. I will only show pictures of work in progress. To find out the details, just keep track of the progress.