The 1st Floor beam soffit formworks and tee supports have been dismantled and moved to the 3rd Floor. Today the workers started to plumb the 3rd Floor columns and also take levels for the 3rd. Floor beams. The progress had slowed down a bit because one of the skilled workers is on leave. The target to concrete the 3rd Floor beams on Thursday may not be met. Most probably it will be delayed by 2 days which means that concreting will be on next Sunday.