30 December 2008

3rd Floor beam in progress


The 1st Floor beam soffit formworks and tee supports have been dismantled and moved to the 3rd Floor. Today the workers started to plumb the 3rd Floor columns and also take levels for the 3rd. Floor beams. The progress had slowed down a bit because one of the skilled workers is on leave. The target to concrete the 3rd Floor beams on Thursday may not be met. Most probably it will be delayed by 2 days which means that concreting will be on next Sunday.

19 November 2008

Concreting Column Stumps


The workers had completed fixing the formworks for the column stumps and had commenced concreting the stumps after checking their alignment. Weather at site was not that fine and was drizzling in the afternoon. The sky is also quite dark. Hopeffully the weather for tomorrow will be fine so that the pace of progress can be kept.