25 December 2008

2nd. Floor Beam completed


Eventhough today is Christmas Day which is a public holiday my workers still work. They managed to finish concreting the 2nd. Floor columns and beams. The mobile crane arrived as expected but I had to pay RM650 instead of RM500 for the rental. Today's weather is rather bad and it has been drizzling interspersed with heavy rain the whole day and luckily my workers managed to complete their works without any interruptions.