03 December 2008

Ground beam and slab ready for concreting

My workers had finished placing the steel reinforcement bars for the ground beams and the BRC for the suspended floors and they are ready to be concreted. I have booked the mobile crane for tomorrow. It will be used to lift the concrete to where it will be poured. With the reduction in fuel price, the operator had agreed to reduce the rental from Rm600 to Rm550 per day. This is still not back to the pre-petrol price hike rate which was RM450 per day.