My workers continued to fixed the soffit (tai pan) for the 1st. Floor. I have to order more 2" x 3 " timber because the quantity on site is not sufficient to make all the props (Ts) for the 1st. Floor Beam. After having check the level and plumb the soffit, the workers will proceed to fix the side formwork before placing the steel reinforment bars. It will take another few days for them to finish the work. Hopefully by the time I goes back on 16th December 2008, the 1st. Floor beam will be ready for concreting. I target this coming Thursday for pouring the concrete.