2nd. Floor beam in progress


My workers have commenced dismantling the T props for the 1st Floor beams. However, they are only taking down alternate props leaving behind props in between to support the beam until the concrete mature and reach the desired strength (at least 14 days). The retrieved props will be used to supplement the new props being constructed (see photo) to support the soffit formwork for the 2nd. Floor beams.


In life, all good things come hard, but wisdom is the hardest to come by.
- Lucille Ball